Work in Progress
5 minute read
Adapted from Dojo Consortium
Definition
Work in Progress (WIP) is the total count of work items that have been started but not yet completed and delivered to production. This includes all types of work: stories, defects, tasks, spikes, and any other items that a team member has begun but not finished.
WIP is a leading indicator from Lean manufacturing. Unlike trailing metrics such as Development Cycle Time or Lead Time, WIP tells you about problems that are happening right now. High WIP predicts future delivery delays, increased cycle time, and lower quality.
Little’s Law provides the mathematical relationship:
If throughput (the rate at which items are completed) stays constant, increasing WIP directly increases cycle time. The only way to reduce cycle time without working faster is to reduce WIP.
How to Measure
- Count all in-progress items. At a regular cadence (daily or at each standup), count the number of items in any active state on your team’s board. Include everything between “To Do” and “Done.”
- Normalize by team size. Divide WIP by the number of team members to get a per-person ratio. This makes the metric comparable across teams of different sizes.
- Track over time. Record the WIP count daily and observe trends. A rising WIP count is an early warning of delivery problems.
Data sources:
- Kanban boards – Jira, Azure Boards, Trello, GitHub Projects, or physical boards. Count cards in any column between the backlog and done.
- Issue trackers – Query for items with an “In Progress,” “In Review,” “In QA,” or equivalent active status.
- Manual count – At standup, ask: “How many things are we actively working on right now?”
The simplest and most effective approach is to make WIP visible by keeping the team board up to date and counting active items daily.
Targets
| Level | WIP per Team |
|---|---|
| Low | More than 2x team size |
| Medium | Between 1x and 2x team size |
| High | Equal to team size |
| Elite | Less than team size (ideally half) |
The guiding principle is that WIP should never exceed team size. A team of five should have at most five items in progress at any time. Elite teams often work in pairs, bringing WIP to roughly half the team size.
Common Pitfalls
- Hiding work. Not moving items to “In Progress” when working on them keeps WIP artificially low. The board must reflect reality. If someone is working on it, it should be visible.
- Marking items done prematurely. Moving items to “Done” before they are deployed to production understates WIP. The Definition of Done must include production deployment.
- Creating micro-tasks. Splitting a single story into many small tasks (development, testing, code review, deployment) and tracking each separately inflates the item count without changing the actual work. Measure WIP at the story or feature level.
- Ignoring unplanned work. Production support, urgent requests, and interruptions consume capacity but are often not tracked on the board. If the team is spending time on it, it is WIP and should be visible.
- Setting WIP limits but not enforcing them. WIP limits only work if the team actually stops starting new work when the limit is reached. Treat WIP limits as a hard constraint, not a suggestion.
Connection to CD
WIP is the most actionable flow metric and directly impacts every aspect of Continuous Delivery:
- Predicts cycle time. Per Little’s Law, WIP and cycle time are directly proportional. Reducing WIP is the fastest way to reduce Development Cycle Time without changing anything else about the delivery process.
- Reduces context switching. When developers juggle multiple items, they lose time switching between contexts. Research consistently shows that each additional item in progress reduces effective productivity. Low WIP means more focus and faster completion.
- Exposes blockers. When WIP limits are in place and an item gets blocked, the team cannot simply start something new. They must resolve the blocker first. This forces the team to address systemic problems rather than working around them.
- Enables continuous flow. CD depends on a steady flow of small changes moving through the pipeline. High WIP creates irregular, bursty delivery. Low WIP creates smooth, predictable flow.
- Improves quality. When teams focus on fewer items, each item gets more attention. Code reviews happen faster, testing is more thorough, and defects are caught sooner. This naturally reduces Change Fail Rate.
- Supports trunk-based development. High WIP often correlates with many long-lived branches. Reducing WIP encourages developers to complete and integrate work before starting something new, which aligns with Integration Frequency goals.
To reduce WIP:
- Set explicit WIP limits for the team and enforce them. Start with a limit equal to team size and reduce it over time.
- Prioritize finishing work over starting new work. At standup, ask “What can I help finish?” before “What should I start?”
- Prioritize code review and pairing to unblock teammates over picking up new items.
- Make the board visible and accurate. Use it as the single source of truth for what the team is working on.
- Identify and address recurring blockers that cause items to stall in progress.